GR from production/ partial lot-Batches
hi
During in process inspection , partail lot/Batches were created.
Is it possible for the system to propose the Batches/partial lot quantities
when doing a GR from production for the PP order.
thanks
Vijay
hi vj
Use transaction CA02 (change routing screen),
got to operation overview.
select an opeartion and press F6 i.e go to operation details
and go to-->
Quality management: inspection points
and check Last p. lot assign
If you set this indicator following will happen (As pasted form F1 help)
Procedure
Set this indicator for the operation that specifies the last inspection
during production and therefore also the last assignments to partial
lots.
Dependencies
Quantity postings from partial lots to the warehouse stock are only
possible with operations for which this indicator is set.
I hope this will solve your problem
set this indicator for your last opeartion..
regrads..
vdheeraj..