PS-Budget Decrese from One WBS and Incrise in Other WBS

Question:
Hi , PS Gurus,
I want to decreise budget of one Wbs and want to incrise in other WBS in same Project.
Pl guide.....
Thanks in Advance
Bal
Answer:
You have the following options:
1) Change original budgets directly using Change budget transaction (CJ30). This is if you do not want to track changes.
2) If you want to track you you can use budget transfer if the budget amount to be reduced is equal to budget amount increased Transaction code CJ34
3) If the both the amount are not same and u need to track them then reduce budget using transaction code CJ35 - Return budget and add budgets using transation code CJ36 - Supplement budget
Regards
Atul Savalia
Answer:
Atul thanks for Help
Bal
B.N.Bhosale
SD/CS/QM/PS Functional Consultant
bhosalebala@yahoo.com

More Articles:

Phantom assy. requirement in other plants?
Open reservations deleted?
Automatic correction after QC UD to process order?
Quantity question for field in COR6 and COR3?
attaching insp. plan ( QP01) to a lot( qa02)?
customer service tables?