Task List Execution Factor

Question:
Dear PM Gurus
Scenerio: In a task list an operation has a component assigned to it. say quantity of 1 widgit. The planned hours for the operation is 1 hour. Now assign the task list to a order and from the order increase the quantity of the widgit to 2. How can I get the execution factor to increase thus increasing my planned hrs. I know it can be done but I don't know where to set this up? Any help will be appreciated.
Racer
Answer:
Racer,
If I understand correctly, you want to know where the Execution Factor field is within the PM/CS order?
Assuming this is correct and your using 4.7, the field can be viewed on the Operations tab. You can change the value by selecting the relevant operation and pressing the Ex. factor" button at the bottom of the screen. Alternatively, if you navigate to the operation General sub-tab you will see Execution Factor field at the top of the tab along with a change button.
If this is not what you were asking, please clarify

More Articles:

Task List update but preventive order no changed!?
what are the Important PP Tables?---urgent?
Link between Documents and Characteristics?
more than one capacity per line in REM?
Problem while running co11n?
Inspection during stock transfer between storage location.?