Question:
hi,
We have maintained safety stock for all the materials.MRP run is based on
demand.Can we take a MRP run without taking into consideraion the
Safety stockof the FG materials??? or is there any other approach for this?
regds
Sancho
Answer:
Hi,
If it is only for "what happens if" purpose, you can take a LTP run and set it to not consider safety stock.
Answer:
Hi
In T.Code OPPR we can leave the average saftey stock as zero so that
the saftey stock won't be included in the planning run
SK
SANKRISH