PM-Maintenance strategy.Transaction code-ip11

Question:
Dear All
I entered following parameters in the strategy.
Scheduling indicator -Time
Strategy unit -MON
Shift factor for late confirmtion -60 %
Tolerence for late confirmation -100%
Factory calender w8.
All above parameters are getting transpered to Strategy Maintenance
Plan (Tran.code ip42) exept factory calender (w
Can any body tell me what will be the cause of problem.
thanks in advance
--------Pramod-----
Answer:
Hi P
scheduling indicator = Time factory calendar does not matter
If you want factory calendar to work choose
scheduling indicator = time-factory calendar.