order schedulling
Hello fans,
We want to schedule the order for month. ie for any date during month as basic start date for forward schedulling, the basic finish date should be the date of month end.
eg.
Basic start date : 02.12.2004, system should give....
Basic finish date : 31.12.2004
If standard SAP provides this facility, can anyone tell me how to configure this?
If not, can anyone tell me the enhancement for order creation/schedulling which can be used to write user exit for this?
Thanks in advance,
Rgds,
this can be solved by using proper lot sizing procedure in material master.
In configuration for Lot Size pls check scheduling indicator setting(t-code OMI4)
regards,
Micky
Dear Micky,
I check the Tx:OMI4, I found only 5 item can be selected in the scheduling field. as follows:
Requirements date := delivery date
1 Period start := delivery date
2 Period end := delivery date
3 Period start := start and period end := delivery date
4 Period start := start date
which one is the proper to solute the topic?
thank you.
TK