Table names for budgets of WBS

Question:
Hello,
I need to know the tables containing the budget figures per cost element.
I saw that COSS and COSP are containing the pre-budget, actuals, etc figures but no budget figures (WRTTP = '41').
I saw also that RPSCO is containing budget figures but not at cost element level.
Does somebody know the table(s) containing the information that I need ?
Thanks a lot and regards,
Guy
Answer:
Guy,
Not at a system, but try COEP or COST

Answer:
This site is a good starting point for table names.
http://www.sapgenie.com/abap/tables.htm

Answer:
Moved it to PS Forum!
ZZ
Answer:
Hi all,
Thanks for the replies and the move to the correct forum.
I was knowing the link given but I did not found the answer there.
COST is only containing pre-budget (WRTTP = '01') in my system and not budget (WRTTP = '41').
COEP contains effectively the data but is difficult to use since it is so huge.
If somebody has another idea, it will be great.
Regards,
Guy
Answer:
Budget is only entered at a WBS level not a Cost element level.
(So I'm not sure how you expect to get Budget by Cost element)
Try table BPGE for Overall Budget values (against the WBS)
Can I ask how you are inputting your "Budget" which t-code?
This will help me more should the table above not give you the correct values
Thanks
Crazy George

More Articles:

Network without activity?
SAP Veteran . but new at PS!?
GR from production/ partial lot-Batches?
How to Creat PM schedule for group of equipment?
Results recording without valuation possible?
service contracts?