New Transaction that could change PO after release

Question:
Hi,
I would like to create a new transaction that is possible to change PO after release.Before submit the request to developing team, could u tell me the probability and basic principle?
Regards,
LEE
Answer:
There is an indicator ' Chgabli.' --Changeability of purchasing document during/after release which is like to help. The indicator is set when define the release indicator.
Greetings,
April
Answer:
Hi,
Alternatively, look at the setting in Transaction OMET with further assignment to the end user with parameter EFB.
Cheers,
HT