Change MRP Results

Question:
Hi all,
i used the search button but didnīt find the right solution, so i will try to descibe it very easy.
Is there any way to change the mrp results for special materials.
For example:
The mrp plans a material with a schedule agreement and makes
new schedule lines. Now i want to change the qty or the date
of this new schedule line for special materials ( in first case only the
schedule line date ).
I found 2 user-exits in the mrp. But these are only to say: PLAN MATERIAL YES/NO.
Does anyone knows an user-exit that can be used in such reasons?
Or has anyone tryed to make such a solution?
Br,
Carsten
Answer:
do you want to say it is not possible to maintain the schedule lines with ME38 ?
Answer:
yes, we can change it in the ME38.
But the problem is, that we have over 300 schedule agreements
which we had to change every day.
ok, i see i must explain the problem a little bit closer.
We produce with a 7 days plant calender. Now it can be, that we
stop the production for one workcenter over weekend. The mrp
donīt realizes this and plans schedule lines to the weekend.
So the vendor sends us the material on that weekend! But we dont work there!
We want to find a way, that all the schedule lines that are planed for the workfree weekend are planed on the next Monday.
Our first try was to search for a user-exit in the mrp, where we can select if it is a workfree weekend and manipulate the mrp results ( schedule lines on monday ).
I hope this is a better explaination.
br,
Carsten
Answer:
Hi,
Have you ever thought of using the time-phased planning feature in SAP which can meet your specific business requirement? Check it out.
Cheers,
HT
_________________
Moderator:

Answer:
Hi,
Have you ever thought of using the time-phased planning feature in SAP which can meet your specific business requirement? Check it out.
Cheers,
HT
Yes, we found that solution too. But we need a more flexibel one!
We use the material from the schedule agreement in several BOMīs and
on several work centers. If we use the time-phased planning, we take effect on every work center ( on the whole production ).
The system should plan the material normal from Monday to Friday ( make normal schedule lines ). On Saterdays and Sundays it should look
if there is work on the work centers or not ( make schedule line YES/NO ).
If the work center does not work, he should plan the schedule line ( with the qty from the weekend ) to the next monday.
Does nobody had this or such a problem befor?
Is there no user-exit that can be used? ( mrp user-exit does not work for this ).
Carsten
Sorry for the lengthy explanation.
Carsten

More Articles:

Planned delivery cost?
scheduling agreements?
Purchase Order Output Messages?
Sub contracting?
Problem I have been trying to solve for 5 years?
Default info.rec indicator ticked for A and K PO.?