Reservation

Question:
Can we have release strategy for reservations? Any work around...
Thanks
Answer:
Hi,
There is not actually such 'release strategy' feature in reservation. The only workaround solution for you is to set up the authorization profile for your end users so that once they do the reservation, they can not be able to flag the 'Goods Movement for reservation allowed' indicator and this activation will be, therefore, given to those who has had the related authorization to 'approve' it.
Cheers,
HT
_________________
Moderator:

More Articles:

Final Invoice Indicator but remaining $ still shows in MIRO?
Subcontracting stock not considered during MRP Run?
Calculations for determining capital spares purchases?
How to make data flow from PR --> PO --> GR?
Creating RFQ before releasing PR?