Multiple Value for Release PO

Question:
I have release strategy for PO use material group as characteristic.
The problem occur when PO contain line item for more than one material group, but in the same release strategy.
Example.
item 1 use material group = electrical sparepart
item 2 use material group = mechanical sparepart
Could you help the problem?
Thanks a Lot,
Eko
Answer:
Hi,
If this is the case, then make sure that you will replicate your existing release strategy into the new set of release strategy with the same release characteristic values except for the material group release characteristic where a 'BLANK' release value should be assigned via Transaction CL20N. Check it out and let me know how it goes.
Cheers,
HT