Change account assignment (CC) in Purchase Order

Question:
Hi,
we have to change the Cost Center in PO for the new Fiscal Year. From the new year on different Cost Centre should be used.
However, the problem I face is that the Cost Centre actually need to be available on the day the PO was created and not on the date the Cost Center should be changed.
How can I solve this in case I do not want to create Cost Center before that?
Heaps thanks
Maurock
Answer:
Hi,
There is one solution which you can use to overcome your problem. Nevertheless, you should be very much careful in using it. That is to set up the 'Cost Center' field as 'optional' field through OME9 Transaction.
Cheers,
HT
_________________
Moderator:

Answer:
Thanks!
I will create CC earlier.
One more question:
how could I do a mass change of the Cost Centre in PO? WE have around 1000 open PO items and it would take some time to manage that.
Reg.
Maurock
Answer:
One more:
Is there a report that shows the Account Assignments/ Cost Centres in (open) PO?
Thanks!
Answer:
Hi,
Is there a report that shows the Account Assignments/ Cost Centres in (open) PO?
Check in Transaction ME2K.
Cheers,
HT
_________________
Moderator:

More Articles:

P.O Header Text?
Asset Procurement?
Period closing MMPV?
This is for the experts. Inbound Delivery based GR?
Slow moving report?
Triangular Trade?