Process loss

Question:
Hi All,
I am sending component B to produce Material A for External processing. Assume that I am sending 1000 Kgs of component B to Manufacture Material A for 1000 KG. In first lot vendor sends the material A for 214 KG and mention in delivery note as 7% of process loss. Hence the total quantity received to stores comes to 200 KG. I want to take full quantity of 200 KG which I have actually received to stock. But want to pay to vendor on 214 because I want to bear the process loss. How to overcome this during goods receipt and invoice verification? Please guide me in this regard.
Answer:
Hi,
Have you looked at the 'Component Scrap' field in the BOM maintenance (Transaction CS01) for your component B?. Check it out.
Cheers,
HT
_________________
Moderator:

Answer:
Hi Tran,
Thank you very much. I have maintained the scrap % in CS02. Now it is working fine. Thanks a lot for your reply
Hi,
Have you looked at the 'Component Scrap' field in the BOM maintenance (Transaction CS01) for your component B?. Check it out.
Cheers,
HT

More Articles:

Determination of best price in purchasing?
Planned orders info to Supplier?
Contracts, Purchase info records and Source lists.?
Gr based Iv flag on Contract?
How to prevent POs been formally outputted?
Error in Goods initial entry?