RFQ creation from Requisition

Question:
Hi MM Gurus,
I have a problem and want your support in solving it.
I create a service Requisition and create RFQ based on that requisition.
when i maintained the quotation which may have different rate than parental requisition.
I have to modify requisition manually as per RFQ rates for the approval.
is it possible that requisition rate may modify as i select the quotation or maintain the quotation.
rgds.
Answer:
Hi, I am not sure why you are changing the value in Requisition.The Requisition value is only indicative. There is flow like Requisition > RFQ > Maintain Quotation > PO and not the vice versa. Hope this will help.
Answer:
You are right regarding the flow.
iwant to approve the requisition by the release strategy on final rates.
otherwise i have to make other release strategy for RFQ also.
I also think that reverse flow is not possible, but may be some one has any idea...
Answer:
Hi AKS,
Why don't you set the Release Strategy at the PO instead of getting the PR approvers to approve the same PR twice once the unit price changes?.
Cheers,
HT