Question:
I am finding my GR and IR buttons to be checked and greyed out. How are these settings controlled? I have made the fields optional using the define screen layout transaction. Also have created a new account assignment category without GR. Even when using this newly created account assignment the GR is checked and grey. Help is greatly appreciated.
Answer:
Hi,
Check in Transaction OME9.
Cheers,
HT
Answer:
Thanks HT,
However, I have checked the configuration settings for both OME9 and OMF2 and all appears as if my GR/IR indicators should be changeable. Unfortunately they are not. What else can affect this?
Answer:
Check transaction OMEB and verify that the purchase requisition document field selection field is the one that you are changing through OMF2.... For example, I tried to change field selection ME51N only to find out that I should be changing field selection "NBB".... Hope this helps ...
Steve ... (USA)
Answer:
Thanks I had checked this as well. Not it. I found that the screen had controls that had to be changed within the screen painter to allow the field to become changeable.
Answer:
Maybe check the info record (me13)?

More Articles:

ABC Indicator in Material Master MRP1 View?
PO report giving error?
New Transaction that could change PO after release?
Change Vendor on PO Manually?
RFQs and attachments together?
WM go-live strategy?