Conversion of requisition into PO
Hello,
When converting two purchase requisitions which contain the same material and are for the same vendor into 1 PO two separate line are created. Is is possible to have one line created for the total amount of that one material ?
Regards,
Guido
I don't think so.
ciao,
lorenzo
are those requisitions created manually or automatically via MRP.
If automatically, then you can change material master MRP4 view field individual/collective requirement to collective.
If you use ME59(N) there is a flag 'generate schedule lines' that will create one PO item out of two requisition items. It will whatever create two schedule line items in that purchase order line item.
yes, you can.
after you create a PO for one purchase requisition, go to item / delivery schedule
you will se a line with the first purchase requisition.... just add the others requisitons bellow, but TAKE CARE with messages about diferent materials.
by the way, I suggest to check the MRP parameters.
good luck
_________________
Fernando A. Tidei
Information Technology