Conversion of requisition into PO

Question:
Hello,
When converting two purchase requisitions which contain the same material and are for the same vendor into 1 PO two separate line are created. Is is possible to have one line created for the total amount of that one material ?
Regards,
Guido
Answer:
I don't think so.
ciao,
lorenzo
Answer:
are those requisitions created manually or automatically via MRP.
If automatically, then you can change material master MRP4 view field individual/collective requirement to collective.
Answer:
If you use ME59(N) there is a flag 'generate schedule lines' that will create one PO item out of two requisition items. It will whatever create two schedule line items in that purchase order line item.
Answer:

yes, you can.
after you create a PO for one purchase requisition, go to item / delivery schedule
you will se a line with the first purchase requisition.... just add the others requisitons bellow, but TAKE CARE with messages about diferent materials.
by the way, I suggest to check the MRP parameters.
good luck
_________________
Fernando A. Tidei
Information Technology

More Articles:

Price difference between PO and Invoice?
Subcontracting, Urgent?
Automatic Creation of PO by batch job - urgent?
exclude mrp requisitions from release strategy?
Deliv Comp ind?
Material Number for Asset Purchased?