pt60 issue

Question:
Dear All
i have substituted(2003) a set of employees for one month on a different work schedule..when i check 0007, its showing me the right work schedule..however, when i checked pt_clstb2 , its not showing the free days(sundays)...and this is happening only for a single employee....this is causing problem in running his pt60 by throwing an error "employee not at work"
can anyone pl let me know whats the reason for this behavior?
_________________
-hS-
Answer:
Hi,
IT 0007 shows the work schedule without any subtitutions.
The work Schedule in Cluster B2 includes all subtitutions.
So if in Cluster B2 a free day is not showing, you have to check the substituion or if there is any dynamic assignment of daily work schedule in your time evaluation shema.
By the way: To see the work schedule including all substitutions of an Employee use the personal work schedule (Report RPTPSH10).
Hope this will help you
best regards
sandra

More Articles:

Daily Work Schedule Class Descriptions in Time Eval?
PG: Do I have to set this in all environment ? auth/no_chec.?
Smart Pensions?
IT0000 and IT0302?
PRBLEM IN ADDING ADDONS IN PHASE IS_SELECT OF BW UPG 21C-30B?
Adding Designation field on Remuneration Statement?